How Long Does a Rental Property Turnover Take?

A day-by-day schedule for a Las Vegas make-ready, what slows turnovers down, and how to protect a lease start date.

7 min read Updated September 2026 By MA Remodel & Repair
How Long Does a Rental Property Turnover Take?

Key takeaways

  • A standard 3-bedroom make-ready takes 3–7 business days when the scope is set before work starts.
  • Light turnovers — paint and a punch list — finish in 1–3 days.
  • Almost every blown deadline traces back to a scope that changed after work began.

The honest answer is that it depends on what is behind the walls — but that is not useful when you have a lease starting in ten days. So here is how long turnovers actually take, and what moves the date.

Day by day, for a standard make-ready

  1. 1

    Day 0 — Walkthrough and written scope

    Photos, measurements, line-item pricing, and a schedule built backwards from your deadline.

  2. 2

    Day 1 — Protect and repair

    Floors and fixtures protected. Move-out damage repaired. Minor plumbing and electrical handled in the same visit.

  3. 3

    Day 2–3 — Drywall, texture, paint

    Patching, texture matching, primer where needed, then two finish coats.

  4. 4

    Day 3–5 — Flooring, trim, doors

    Old flooring removed, subfloor corrected, new flooring installed, baseboards and doors set and caulked.

  5. 5

    Day 5–6 — Fixtures and punch

    Hardware, blinds and fixtures reinstalled. Punch list walked. Touch-up paint and final caulk.

  6. 6

    Day 7 — Handoff

    Final walkthrough, photo set, itemized invoice, keys returned.

The single biggest variable

Flooring. Paint and drywall move on a predictable clock because dry time is fixed. Flooring depends on material lead time and subfloor condition, so it is the item most likely to move your date.

What slows a turnover down

  • A scope that changed after work started — the most common cause of a missed date.
  • Undiscovered moisture. Testing happens on day one, not day four, for exactly this reason.
  • Material lead time on flooring, tile, vanities or specialty trim.
  • Subfloor repair discovered under old flooring.
  • A unit that was never fully emptied by the outgoing tenant.
  • Scheduling trades separately. Five vendors means five schedules and five chances to slip.

Timelines by job type

JobTypical duration
Paint and punch list only1–3 business days
Standard 3BR / 2BA make-ready3–7 business days
Make-ready with full flooring replacement5–9 business days
Bathroom renovation2–3 weeks
Kitchen renovation3–4 weeks
Mold remediation, single room, plus rebuild1–2 weeks

How to protect your lease start date

  • Give the contractor the deadline up front, not after the scope is set.
  • Get the scope in writing, with line-item pricing, before work starts.
  • Sequence listing-critical work first: paint, flooring, drywall and curb details.
  • Choose materials from what is in stock locally rather than waiting on a special order.
  • Keep one point of contact so decisions get made the same day.

What we typically see in Las Vegas homes

Based on our own repair work

What we see on the schedule side, from running multi-unit turnovers every month:

  • The two things that reliably blow a deadline are flooring lead time and a scope change. Almost nothing else moves a date materially.
  • Rushing paint is a false economy. Coat two applied before coat one has dried looks fine on day six and telegraphs by month three.
  • Scheduling every trade on one schedule is the single biggest time saver. Most of the delay we are called in to fix comes from waiting on a second or third vendor.
  • Summer is slower, not faster. Cure times for caulk, paint and grout all run longer in a Las Vegas July, and a unit with the air off runs longer still.
Real Las Vegas project
Problem

A property manager had a lease starting in nine days on a Henderson unit that had been vacant for two months, with worn carpet, marked walls and a bathroom that had not been touched in years.

Our solution

Ran the walkthrough the same day and wrote the scope, then sequenced it deliberately: flooring ordered first so it was on site before demolition, drywall and paint run while the flooring acclimated, flooring installed on days three and four, then fixtures, trim, caulk and punch. Handed back on day seven, two days ahead of the lease.

Location

Henderson, NV

Common questions

The questions we get asked most about this, answered plainly.

Have a property that needs work?

Free estimates with a written, line-item scope — usually within 24 to 48 hours. Tell us the address and the deadline and we will tell you plainly what it takes.

NV State Licensed · Fully Insured · CMRC Certified Mold Remediation